Greg:

  • Repair keel - Greg. Greg has made good progress, Franny will push for him to complete the keel for launch.
  • Paint bottom.

Greg should provide guidance wrt bottom, mast/boom and topsides painting.

Lloyd:

  • Fix engine oil leaks - Lloyd. Lloyd says he’s on this; I’ll keep pushing him. No real Plan B if Lloyd doesn’t move on this; I think we need to pull the engine to do the job right.

Eric:

  • Remove corrosion on mast and boom; repaint - Eric We should work on the boom and the mast. No progress on this yet that I know of.
  • Binnacle light - Eric (can be done after splash)

Scott:

  • Replace nuts on rear quarter fittings - Scott
  • New blocks for mainsheet - Scott These are on the boat.
  • New shackles to fasten traveler adjusting blocks to car - Scott.
  • Inspect running rigging - Scott. Done. Need to take a length of rigging to the riggers for work.
  • Take harnesses/jacklines/foulies/radios&plugs/puck compass/ditch bag/laptop/iPad to boat. Halyards and blocks and pfds on boat.

Ted:

  • Replace damaged NMEA terminator for anemometer on masthead - Ted
  • Inspect steering gear, grease rudderpost - Ted
  • Condition batteries - Ted. I have no idea where this is at.
  • Cetol woodwork - Ted. Scott applied a couple of coats of Cetol to the worst parts last Fall; we should put on a couple of coats more.

Adam:

  • Repair dodger - Adam
  • Get main, #1, #3 and spinnaker from North

Tim:

  • Restitch wheel cover

Other:

  • Take cushions from pav to boat (shortly before launch)
  • Take boom to boat
  • Inflate red dinghy, coat with ArmorAll, move to Waterboat.
  • Clean, buff and Propspeed prop (think there is propspeed at the pav)
  • Replace prop shaft zincs